State Steps Up Enforcement for Uncleared Digs as Utility Strikes Mount

The California Dig Safe Board is increasing investigations into uncleared excavations, exposing fence contractors who fail to use the 811 system to fines of up to $50,000.
July 21, 2026

California fence contractors face serious civil penalties for bypassing 811 utility locate requests. Utility operators across the state report that unnotified digging by contractors remains a leading cause of pipeline and electrical damage. In response, state safety officials are tracking down unreported excavations and penalizing offenders.

The California Underground Facilities Safe Excavation Board (the Dig Safe Board), an agency within the Office of Energy Infrastructure Safety, possesses the statutory authority to investigate dig incidents. Under California Government Code § 4216, the Board can recommend civil penalties up to $10,000 for negligent violations and up to $50,000 for knowing and willful non-compliance. Fines escalate to $100,000 if an excavator ruptures a pipeline and releases flammable, toxic, or corrosive gas.

For fence installers relying on mechanical augers, understanding the mechanics of California excavation law is essential.

 

1. Why is the state investigating unticketed digging more aggressively?

Contractors routinely damage underground lines without opening an 811 ticket, leaving incidents unreported. To close this gap, the Board partners with utility operators to track these damages, catch unpermitted digs, and initiate formal investigations.

2. Why do fence contractors face a high risk of utility strikes?

Fence builders sink narrow, deep post holes along lot lines where private utility service drops cross from street mains to structures. Due to soil erosion or improper initial burial, secondary electrical lines, irrigation mains, and gas drops often sit at unpredictable depths. A mechanical auger bit severs unarmored fiber, conduit, or plastic gas pipe in seconds.

3. Why do field crews dig without legal clearance?

Crews misinterpret the mandatory two-working-day waiting period as an automatic authorization to dig. Government Code § 4216 requires excavators to wait two working days and receive an electronic positive response from all regional utility operators. The law forbids digging until every operator listed on the ticket confirms the site is marked or clear.

4. Why do strikes occur even after utilities mark the site?

Excavators ignore the statutory tolerance zone. State law defines the "tolerance zone" as 24 inches on each side of the field marking, assuming the mark represents the centerline of the subsurface installation. Inside this 24-inch zone, contractors must use hand tools to expose the exact location of the facility before using power-driven equipment.

5. Why do contractors lose damage disputes?

Contractors fail to document their compliance. Without clear evidence, state investigators presume negligence. A sound defense requires proof that the contractor white-lined the dig boundaries before calling 811, secured verified positive responses from every operator, and respected the 24-inch tolerance zone.

 

Jobsite Compliance Checklist for Fence Installers

  • White-Line the Work Zone: Mark the proposed post holes with white paint or flags before submitting the 811 ticket.
  • Demand Positive Responses: Check the ticket status through USA North 811 or DigAlert. Confirm every utility operator listed on the ticket has responded before starting an auger.
  • Hand-Dig the Tolerance Zone: Stop using power tools when working within 24 inches of the outer edge of any utility mark. Use hand tools to expose the line.